Click on button below to view pictures and
information
TREATMENT
PLANT
RESERVOIRS (OLD & NEW)
W. STATE ST.
BRIDGE (OLD & NEW)
CLICK ON A PICTURE TO ENLARGE IT, THEN CLICK YOUR BACK
BUTTON TO RETURN TO THIS PAGE

Intake
In 1981 serious erosion
of the old Sinclair landfill and pollution of the river was discovered. This
problem was placed on the "Superfund" list and given a high priority
nationwide because of the threat to the water supply. New York State DEC, using
funds supplied by ARCO, successor to Sinclair Refining Co. built a new intake,
pump station and transmission line upstream of the refinery site. This intake
was turned over to the Village in 1988.
|
|
|
|
|
|
|
|
|
View of the intake channel to the intake as well as partial view of the intake weir being constructed. |
|
|
|
|
|
|
|
|
|
|
|
|
Driving the pilings in the Genesee River for the current intake. |
|
|
|
|
|
|
|
|
|
|
|
|
The Genesee River can change instantly as shown here. |
|
|
|
|
|
|
|
|
|
|
|
|
This is a view looking down into one of two pits at the intake. Each pit contains two pumps, (one 15 & one 25 hp). |
|
|
|
|
|
|
|
Treatment
Plant
Construction began in
June 1989 for the new treatment plant and it went in to service June 1990.
This plant has a 500,000 gallon clearwell. We have plenty
of room for growth as we are currently operating 80 hours per week.
|
|
|
The old Water & Light plant. At one time we generated our own electricity and provided heat to the school, hospital and library through steam lines. |
|
|
|
This view is of our current treatment plant, we went on line June 1990 |
|
|
|
Setting the filters in place before erecting the building. Each filter can filter 1 million gallons per day. |
|
|
|
Constructing the new plant. |
|
|
|
The clearwell, which holds 500,000 gallons allows our chemicals to have a minimum of a four hour contact time with the treated water before leaving the plant. |
|
|
Reservoir
The steel reservoir was
removed from service and demolished because of structural damage in the fall of 1997. The
following three pictures show the demolition.
|
|
|
|
|
|
|
|
|
Starting to demolish our 750,000 gallon reservoir. |
|
|
|
|
|
|
|
|
|
|
|
|
Continuing demolition because of structural failure. |
|
|
|
|
|
|
|
|
|
|
|
|
Nearing completion of the tank demolition. Our first new tank will be set just south of this site. |
|
|
|
|
|
|
|
Old Open Reservoir
Demolition
1916 - 2001
|
|
|
Draining the open 3 million gallon reservoir for the last time. 06/27/2001
|
|
|
|
Aerial view of our 3 million gallon open reservoir while our first Natgun reservoir is being constructed.
|
|
|
|
The rebar in the old reservoir walls 06/29/2001
|
|
|
|
Another view of the rebar in the walls of the old reservoir. 06/29/2001
|
|
|
Construction of two Natgun reservoirs
04/01/01 - Two 2 million gallon reservoirs are now under
construction by Natgun
Corporation
|
|
|
|
|
|
|
Site for our first new reservoir - 04/04/2001 |
|
|
|
|
|
|
|
|
|
|
|
|
Pumping cement for the floor - 04/25/01 |
|
|
|
|
|
|
|
|
|
|
|
|
Stacking the side panels - 04/25/2001 |
|
|
|
|
|
|
|
|
|
|
|
|
Dome panel supports - 05/05/2001 |
|
|
|
|
|
|
|
|
|
|
|
|
Gap between side panels - 05/08/2001 |
|
|
|
|
|
|
|
|
|
|
|
|
Spraying the shotcrete on the upper parts - 05/15/2001 |
|
|
|
|
|
|
|
|
|
|
|
|
Putting on the primer coat - 06/05/2001 |
|
|
|
|
|
|
|
|
|
|
|
|
Dana on top of finished tank - 06/08/2001 |
|
|
|
|
|
|
|
|
|
|
|
|
Now ready for tank #2 - 07/20/2001 |
|
|
|
|
|
|
|
|
|
|
|
|
Crew pouring the floor - 08/01/2001 |
|
|
|
|
|
|
|
|
|
|
|
|
Flooding the floor after concrete poured - 08/01/2001 |
|
|
|
|
|
|
|
|
|
|
|
|
75% of the dome panels in place - 08/22/2001 |
|
|
|
|
|
|
|
|
|
|
|
|
Dome ring supports - 08/28/2001 |
|
|
|
|
|
|
|
|
|
|
|
|
Removing the inside scaffolding - 09/11/2001 |
|
|
|
|
|
|
|
|
|
|
|
|
Applying the last coat - 10/02/2001 |
|
|
|
|
|
|
|
|
|
|
|
|
Wall plaque installed on #2 tank |
|
|
|
|
|
|
|
|
|
10/02/01 - The last coat of paint has been applied.
The access ladder, safety rails, top hatch and dome vent have been installed.
NATGUN is done with the construction of #2 tank.
Landscaping around new
Natgun reservoirs
|
|
|
Showing our 2nd tank from our 1st tank, during the backfill operation. |
|
|
|
Backfilling around our 2nd reservoir. |
|
|
|
Grading around the 2nd tank. |
|
|
|
Finishing up the landscaping. |
|
|
|
Another view of the final landscaping. |
|
|
West State Street Bridge
Demolition
The old state street bridge was
demolished to make way for a new one. 05/15/01
|
|
|
|
|
|
|
|
|
Starting the demolish the old W. State St. Bridge. |
|
|
|
|
|
|
|
|
|
|
|
|
The remaining bridge structure hitting the river. |
|
|
|
|
|
|
|
|
|
|
|
|
The old W. State St. Bridge is down and ready to construct its replacement. |
|
|
|
|
|
|
|
Building the new W. State St. Bridge
06/03/02 - The ribbon has been cut and the
new bridge is officially open after 364 days of being out of service.
|
|
|
Constructing the coffer dam, this holds out the water while the center support structure is being constructed. |
|
|
|
Driving the pilings for the west side supports. |
|
|
|
View inside the coffer dam of the piles that are driven in the river bottoom. |
|
|
|
The west side support structure. |
|
|
|
Setting the first beam. |
|
|
|
|
All of the beams have been set. |
|
|
|
The gas line is installed underneath. |
|
|
|
The phone lines are installed underneath. |
|
|
|
Close up of the rebar for this bridge. |
|
|
|
After the bridge has been poured, it is now being grooved to assist in water runoff. |
|
|
|
|
Finally, the bridge is officially opened. |
|
|
GO TO THE TOP
OF THE PAGE
|